Factory Overview

Factory No. 1
Operation | April 2007 |
Total floor area | 8,822㎡ (Including warehouse : 1,130㎡) |
Production item | Precision Mechanical Components |

Factory No. 2
Operation | November 2013 |
Total floor area | 3,587㎡(Cleanroom area : 2,940㎡) |
Cleanness | Injection molding area - Class 100,000 Coating, Inspection, Assembly area - Class 10,000 |
Production item | Assembly of Optical Units and Mechanical Units |
Factory No. 3
Operation | April 2019 |
Total floor area | 19,896㎡ (Two-story) |
Withstand load | 1st Floor : 1.0 ton/㎡ 2nd Floor : 0.8 ton/㎡ |
Production item | Precision Mechanical Mold Optical Mold Precision Mechanical Components |